Willoughby Leisure Centre Upgrade
Construction work is now underway to upgrade the Willoughby Leisure Centre to create a modern, best in breed new aquatic and recreation facility.
During this upgrade, which will run until 2025, the centre's:
- School holiday program and gym will continue to operate
- Indoor courts will predominantly remain open, but may need to close for some period during construction; and
- Pool hall and creche will remain closed
This page has been created to let people know about the improvements, along with news on any impacts on key users during the construction process.
Construction work is now underway to upgrade the Willoughby Leisure Centre to create a modern, best in breed new aquatic and recreation facility.
During this upgrade, which will run until 2025, the centre's:
- School holiday program and gym will continue to operate
- Indoor courts will predominantly remain open, but may need to close for some period during construction; and
- Pool hall and creche will remain closed
This page has been created to let people know about the improvements, along with news on any impacts on key users during the construction process.
-
Latest project update - October 2024
Share Latest project update - October 2024 on Facebook Share Latest project update - October 2024 on Twitter Share Latest project update - October 2024 on Linkedin Email Latest project update - October 2024 linkConstruction progress on site over last month
- Concourse slab around pools is predominately complete
- Family Change Room – Walls & columns poured
- Upper plant room – Concrete slab above family change room complete
- Concrete walls around eastern spa area poured
- Water testing of pools
- Scaffold ‘bird cage’ installed for steel framework construction
- Ring beam to support the pool hall’s structural steel complete
Focus of construction work in coming month
- Structural steel delivery to site
- Erection of structural steel columns & beams for northern end of the site
- Completion of pool cover concrete boxes
- Completion of concourse slab
- Existing plant room slab integration
- Filtration pipes to southern wall void to be installed
- Completion of slab base for Electrical Sub Station
Completed works
Since the pool closed on 19 November 2022, the following works have been completed:
- Site establishment
- Demolition of the old pool hall
- Implementation of Environmental Protection Authority (EPA) approved Asbestos Management Plan protocols with excavation and removal of some asbestos contaminated soil.
- Construction of new piles to support the pool hall
- Structural retaining wall on the site’s north-eastern boundary completed
- Capping of contaminated soil on 100% of the site
- New stormwater line in Small Street
- Below ground backwash tanks for the 25m and program pools
- Pool Concrete shells are complete for the 25m Pool, Program Pool, Learn to Swim Pool and Spa
- Concrete ring beams to support steel columns
Other relevant project updates over the last month
- A new time lapse video, showing construction between January and July 2024, has been added to the project website.
- Continuation of the Asbestos Management Plan - daily air monitoring continuing
Centre facilities currently open
- Health club and sports hall, including a full range of land-based group fitness classes
Expected project completion date
- 2025
Project photographs from October 2026.
-
Latest project update - September 2024
Share Latest project update - September 2024 on Facebook Share Latest project update - September 2024 on Twitter Share Latest project update - September 2024 on Linkedin Email Latest project update - September 2024 linkConstruction progress on site over last month
- Leisure pool – concrete base and walls poured
- Program Pool – pool covers - concrete poured
- Family change room – concrete slab poured
- Concrete poured for ring beam to support the pool hall’s structural steel underway
Focus of construction work in coming month
- Concrete pour for a portion of the pool hall concourse slab
- 25m Pool – concrete pour for ramps
- Program Pool – pour pool cover base
- Spa – concourse – concrete pour
- Commence erection of scaffolding to construction steel framework
- Steel framework for northern end of pool hall due to arrive on site
Completed works
Since the pool closed on 19 November 2022, the following works have been completed:
- Site establishment
- Demolition of the old pool hall
- Implementation of Environmental Protection Authority (EPA) approved Asbestos Management Plan protocols with excavation and removal of some asbestos contaminated soil.
- Construction of new piles to support the pool hall
- Structural retaining wall on the site’s north-eastern boundary completed
- Capping of contaminated soil on 100% of the site
- New stormwater line in Small Street
- Below ground backwash tanks for the 25m and program pools
- Pool Concrete shells are complete for the 25m Pool, Program Pool, Learn to Swim Pool and Spa
Other relevant project updates over the last month
- A new time lapse video, showing construction between January and July 2024, has been added to the project website.
- Continuation of the Asbestos Management Plan - daily air monitoring continuing
Centre facilities currently open
- Health club and sports hall, including a full range of land-based group fitness classes
Expected project completion date
- 2025
View of completed pool shells
Family change room – concrete slab pour
-
Timelapse video January to July 2024
Share Timelapse video January to July 2024 on Facebook Share Timelapse video January to July 2024 on Twitter Share Timelapse video January to July 2024 on Linkedin Email Timelapse video January to July 2024 link -
Announcements
Share Announcements on Facebook Share Announcements on Twitter Share Announcements on Linkedin Email Announcements linkOn Tuesday, 3rd September 2024, there will be increased truck movements and noise as Belmadar undertake a large and complex pour concrete pour for the Leisure Splashpad pool. This the final pool to be poured and due to the number of water features it includes, may take longer than planned. Nearby residents have been notified of the works.
-
Latest project update - August 2024
Share Latest project update - August 2024 on Facebook Share Latest project update - August 2024 on Twitter Share Latest project update - August 2024 on Linkedin Email Latest project update - August 2024 linkConstruction progress on site over last month
25m pool – concrete shell for pool and pool covers complete
Program Pool – concrete shell complete
Learn to Swim pool – concrete shell complete
Subfloor plumbing for the water jets and play features and concrete pour for the Childrens Leisure Pool completed
Spa walls concrete shell complete and pool cover base poured
Family change room – formwork commenced
Formwork for the ring beam to support the pool hall’s structural steel underway
Focus of construction work in coming month
Leisure Pool – pour concrete to base slab & walls on the 3rd September 2024
Work will progress with the pool hall concourse concrete slab
25m Pool – concrete pour for ramps
Program Pool – pour pool cover Base
Spa – pour blanket cover walls
Family Change Room – pour floor slab
Completed works
Since the pool closed on 19 November 2022, the following works have been completed:
Site establishment
Demolition of the old pool hall
Implementation of Environmental Protection Authority (EPA) approved Asbestos Management Plan protocols with excavation and removal of some asbestos contaminated soil.
Construction of new piles to support the pool hall
Structural retaining wall on the site’s north-eastern boundary completed
Capping of contaminated soil on 100% of the site
New stormwater line in Small Street
Below ground backwash tanks for the 25m and program pools
Pool Concrete shells are complete for the 25m Pool, Program Pool, Learn to Swim Pool and Spa
Other relevant project updates over the last month
Continuation of the Asbestos Management Plan - daily air monitoring continuing
Centre facilities currently open
Health club and sports hall, including a full range of land-based group fitness classes
Expected project completion date
2025
-
Timelapse Video - September 2023 - January 2024
Share Timelapse Video - September 2023 - January 2024 on Facebook Share Timelapse Video - September 2023 - January 2024 on Twitter Share Timelapse Video - September 2023 - January 2024 on Linkedin Email Timelapse Video - September 2023 - January 2024 link
Follow Project
FAQs
-
About the construction process
- 1) What are some of the construction challenges which have been encountered?
- 2) What does this mean for the project timeline?
- 3) What does this mean for the project budget?
- 4) How are you managing the asbestos situation?
- 5) What due diligence has Council undertaken for this project?
- 6) How can the community know they are getting value for money?
- 7) How are the impacts of construction being managed?
- 8) Apart from asbestos, are there other contaminants which are of concern at the construction site?
- 9) What sustainability measures will be included in the new pool area?
- 10) Will the new facility be accessible for everyone, including people with limited mobility?
- Impacts on centre members and hirers during the construction process
Who's Listening
-
JG
Phone 9777 7733 Email Joseph.Giandomenico@willoughby.nsw.gov.au -
GS
Phone 9958 5799 Email Gordon.smith@willoughby.nsw.gov.au