Latest Project update - December 2024

Construction progress on site December 2024

• Major structural steel (columns & curved roof beams) erection on northern sector of the site complete

• Additional concourse slab around pools complete

• Hydraulic and electrical enabling works for pool commenced


Focus of construction work in coming month

• Structural steel (Columns & curved roof beams) erection on southern sector of the site

• Delivery to site of electrical substation

• Surface preparation for floor finishes/tiling on Learn to Swim Pool & Leisure Pool

• Existing plant room slab integration


Completed works

Since the pool closed on 19 November 2022, the following works have been completed:

• Site establishment

• Demolition of the old pool hall

• Implementation of Environmental Protection Authority (EPA) approved Asbestos Management Plan protocols with excavation and removal of some asbestos contaminated soil.

• Construction of new piles to support the pool hall

• Structural retaining wall on the site’s north-eastern boundary completed

• Capping of contaminated soil on 100% of the site

• New stormwater line in Small Street

• Below ground backwash tanks for the 25m and program pools

• Pool Concrete shells are complete for the 25m Pool, Program Pool, Learn to Swim Pool and Spa

• Concrete ring beams to support steel columns

• Concrete slabs for upper level plant rooms

• Structural steel columns & roof beams to northern sector of the site

Other relevant project updates over the last month