Latest Project update - December 2024
Construction progress on site December 2024
• Major structural steel (columns & curved roof beams) erection on northern sector of the site complete
• Additional concourse slab around pools complete
• Hydraulic and electrical enabling works for pool commenced
Focus of construction work in coming month
• Structural steel (Columns & curved roof beams) erection on southern sector of the site
• Delivery to site of electrical substation
• Surface preparation for floor finishes/tiling on Learn to Swim Pool & Leisure Pool
• Existing plant room slab integration
Completed works
Since the pool closed on 19 November 2022, the following works have been completed:
• Site establishment
• Demolition of the old pool hall
• Implementation of Environmental Protection Authority (EPA) approved Asbestos Management Plan protocols with excavation and removal of some asbestos contaminated soil.
• Construction of new piles to support the pool hall
• Structural retaining wall on the site’s north-eastern boundary completed
• Capping of contaminated soil on 100% of the site
• New stormwater line in Small Street
• Below ground backwash tanks for the 25m and program pools
• Pool Concrete shells are complete for the 25m Pool, Program Pool, Learn to Swim Pool and Spa
• Concrete ring beams to support steel columns
• Concrete slabs for upper level plant rooms
• Structural steel columns & roof beams to northern sector of the site
Other relevant project updates over the last month