Latest Project Update – March 2025
Construction progress on site over last month
- Timber Purlins – Installation of main & intermediate purlins
- Plant room waterproof floor and installation of insulation & Pool Filters
- Installation of Electrical Substation
- Official testing of all pool shells
- Plant room services fit out
- Installation of roof liner
Focus of construction work in coming month
- Installation of roofing on pool hall
- Installation of Ceiling
- Preparation works for new Platform Lift
- Completion of Scaffolding around the existing sports hall & central spine
- Commencement of re-roofing of existing sports hall
Completed works
- Since the pool closed on 19 November 2022, the following works have been completed:
- Site establishment
- Demolition of the old pool hall
- Implementation of Environmental Protection Authority (EPA) approved Asbestos Management Plan protocols with excavation and removal of some asbestos contaminated soil.
- Construction of new piles to support the pool hall
- Structural retaining wall on the site’s north-eastern boundary completed
- Capping of contaminated soil on 100% of the site
- New stormwater line in Small Street
- Below ground backwash tanks for the 25m and program pools
- Pool Concrete shells are complete for the 25m Pool, Program Pool, Learn to Swim Pool and Spa
- Concrete ring beams to support steel columns
- Concrete slabs for upper level plant rooms
- Structural steel columns & roof beams to northern & southern sector of the site
- Steel framed wall on Eastern side
- Installation of new Electrical Substation
- Timber Purlins
Other relevant project updates over the last month
Continuation of the Asbestos Management Plan - daily air monitoring continuing
Centre facilities currently open, including the Health club and sports hall. The sports hall will be closed from mid-April 2025 during re-roofing works.
Expected project completion date 2025
Share Latest Project Update – March 2025 on Facebook
Share Latest Project Update – March 2025 on Twitter
Share Latest Project Update – March 2025 on Linkedin
Email Latest Project Update – March 2025 link
