Latest Project Update – March 2025

Construction progress on site over last month

  • Timber Purlins – Installation of main & intermediate purlins
  • Plant room waterproof floor and installation of insulation & Pool Filters
  • Installation of Electrical Substation
  • Official testing of all pool shells
  • Plant room services fit out
  • Installation of roof liner

Focus of construction work in coming month

  • Installation of roofing on pool hall
  • Installation of Ceiling
  • Preparation works for new Platform Lift
  • Completion of Scaffolding around the existing sports hall & central spine
  • Commencement of re-roofing of existing sports hall

Completed works

  • Since the pool closed on 19 November 2022, the following works have been completed:
  • Site establishment
  • Demolition of the old pool hall
  • Implementation of Environmental Protection Authority (EPA) approved Asbestos Management Plan protocols with excavation and removal of some asbestos contaminated soil.
  • Construction of new piles to support the pool hall
  • Structural retaining wall on the site’s north-eastern boundary completed
  • Capping of contaminated soil on 100% of the site
  • New stormwater line in Small Street
  • Below ground backwash tanks for the 25m and program pools
  • Pool Concrete shells are complete for the 25m Pool, Program Pool, Learn to Swim Pool and Spa
  • Concrete ring beams to support steel columns
  • Concrete slabs for upper level plant rooms
  • Structural steel columns & roof beams to northern & southern sector of the site
  • Steel framed wall on Eastern side
  • Installation of new Electrical Substation
  • Timber Purlins

Other relevant project updates over the last month

Continuation of the Asbestos Management Plan - daily air monitoring continuing

Centre facilities currently open, including the Health club and sports hall. The sports hall will be closed from mid-April 2025 during re-roofing works.

Expected project completion date 2025