Latest project update - November 2024.
Construction progress on site over last month
- Concourse slab around pools complete
- Leakage test passed for Learn to Swim Pool & Program Pool
- Scaffold ‘bird cage’ installed for steel framework construction
- Structural steel (Columns & curved roof beams) erection on northern sector of the site
Focus of construction work in coming month
- Structural steel (Columns & curved roof beams) erection on southern sector of the site
- Delivery to site of electrical substation
- Surface preparation for floor finishes/tiling on Learn to Swim Pool & Leisure Pool
- Existing plant room slab integration
Completed works
Since the pool closed on 19 November 2022, the following works have been completed:
- Site establishment
- Demolition of the old pool hall
- Implementation of Environmental Protection Authority (EPA) approved Asbestos Management Plan protocols with excavation and removal of some asbestos contaminated soil.
- Construction of new piles to support the pool hall
- Structural retaining wall on the site’s north-eastern boundary completed
- Capping of contaminated soil on 100% of the site
- New stormwater line in Small Street
- Below ground backwash tanks for the 25m and program pools
- Pool Concrete shells are complete for the 25m Pool, Program Pool, Learn to Swim Pool and Spa
- Concrete ring beams to support steel columns
- Concrete slabs for upper level plant rooms
- Structural steel columns & roof beams to northern sector of the site
Other relevant project updates over the last month
- Continuation of the Asbestos Management Plan - daily air monitoring continuing
Centre facilities currently open
- Health club and sports hall, including a full range of land-based group fitness classes
Expected project completion date
- 2025
Share Latest project update - November 2024. on Facebook
Share Latest project update - November 2024. on Twitter
Share Latest project update - November 2024. on Linkedin
Email Latest project update - November 2024. link