Latest project update - August 2024
Construction progress on site over last month
25m pool – concrete shell for pool and pool covers complete
Program Pool – concrete shell complete
Learn to Swim pool – concrete shell complete
Subfloor plumbing for the water jets and play features and concrete pour for the Childrens Leisure Pool completed
Spa walls concrete shell complete and pool cover base poured
Family change room – formwork commenced
Formwork for the ring beam to support the pool hall’s structural steel underway
Focus of construction work in coming month
Leisure Pool – pour concrete to base slab & walls on the 3rd September 2024
Work will progress with the pool hall concourse concrete slab
25m Pool – concrete pour for ramps
Program Pool – pour pool cover Base
Spa – pour blanket cover walls
Family Change Room – pour floor slab
Completed works
Since the pool closed on 19 November 2022, the following works have been completed:
Site establishment
Demolition of the old pool hall
Implementation of Environmental Protection Authority (EPA) approved Asbestos Management Plan protocols with excavation and removal of some asbestos contaminated soil.
Construction of new piles to support the pool hall
Structural retaining wall on the site’s north-eastern boundary completed
Capping of contaminated soil on 100% of the site
New stormwater line in Small Street
Below ground backwash tanks for the 25m and program pools
Pool Concrete shells are complete for the 25m Pool, Program Pool, Learn to Swim Pool and Spa
Other relevant project updates over the last month
Continuation of the Asbestos Management Plan - daily air monitoring continuing
Centre facilities currently open
Health club and sports hall, including a full range of land-based group fitness classes
Expected project completion date
2025