February Update

During February an exciting milestone was reached with the pouring of the slab for the plant room. Work has now begun on constructing the structural wall that will separate the plant room from the 25m pool and program pool at the lower ground floor level. About two thirds of the site now has a concrete capping layer, an important element of the asbestos management of the site. Installing this capping layer has enabled site contractors to work on those parts of the site in a much more efficient manner. Bulk and detailed excavation is underway on the Learn to Swim and Leisure pools, in the Small Street end of the site and around the perimeter retaining walls on the Flat Rock Gully Road side of the site.